Our Works
Projects
Ongoing Projects
Accomplished Projects
Ongoing Projects
CLIENT:
National Trust for Nature Conservation
DURATION:
From Jestha 2078 (3 months)
WORK ACCOMPLISHED:
National Trust for Nature Conservation
DURATION:
From Jestha 2078 (3 months)
WORK ACCOMPLISHED:
- Topographic survey of the alignment of solar electric fencing including preparation of L-Section and X-Section profiles
- Detailed design of solar electric fencing for preventing elephants from coming in contact to communities
- Detailed cost estimates of the solar electric fencing
- Preparation of bidding documents for procurement of solar electric fencing
CLIENT:
ERMC (P) Ltd, EcoCoDE Nepal (P) Ltd and CMS Engineering Consult (P) Ltd J/V (for Babai Irrigation Project)
DURATION:
From 27 April 2021 (Six months)
WORK ACCOMPLISHED:
ERMC (P) Ltd, EcoCoDE Nepal (P) Ltd and CMS Engineering Consult (P) Ltd J/V (for Babai Irrigation Project)
DURATION:
From 27 April 2021 (Six months)
WORK ACCOMPLISHED:
- Detail topographic survey of irrigation command area of about 1000 hectares
- Detailed design of command area development of six Branch systems of Babai Irrigation Project, Eastern Main Canal
- Irrigation and drainage network planning and design of irrigation and drainage network and structures
- Cost estimate of command area development works of six branch systems
- Preparation of bidding documents for procurement of command area development works
CLIENT:
Rong Rural Municipality, Kolbung, Ilam
DURATION:
From 6 Baisakh 2078 (six months)
WORK ACCOMPLISHED:
Rong Rural Municipality, Kolbung, Ilam
DURATION:
From 6 Baisakh 2078 (six months)
WORK ACCOMPLISHED:
- Detailed architectural plan of hospital building
- Landscaping of the plot including roads, building blocks
- Structural design of hospital building
- Detailed plan of electricity, water supply and sanitation system
- Cost estimate of hospital building
- Preparation of bidding documents
CLIENT:
ERMC (P) Ltd, HCEL and Aviyaan Consulting (P) Ltd J/V (for Babai Irrigation Project)
DURATION:
From 7 July 2021 (16 months)
WORK ACCOMPLISHED:
ERMC (P) Ltd, HCEL and Aviyaan Consulting (P) Ltd J/V (for Babai Irrigation Project)
DURATION:
From 7 July 2021 (16 months)
WORK ACCOMPLISHED:
- Detail topographic survey of irrigation command area of about 6000 hectares.
- Detailed design of command area development of Babai Irrigation Project, tail of Western Main Canal
- Irrigation and drainage network planning and design of irrigation and drainage network and structures
- Cost estimate of command area development works of branch systems
- Preparation of bidding documents for procurement of command area development works
CLIENT:
Rani Jamara Kulariya Irrigation Project, Tikapur, Kailali
DURATION:
From 30 April 2021 (5 months)
WORK ACCOMPLISHED:
Rani Jamara Kulariya Irrigation Project, Tikapur, Kailali
DURATION:
From 30 April 2021 (5 months)
WORK ACCOMPLISHED:
- Review of hydrological analysis/hydraulic analysis and structural design of three bridges over Pathraiya River
- Detailed structural design of three bridges
- Detailed cost estimate of the three bridges.
Accomplished Projects
2021
CLIENT:
Bagmati Irrigation Project, Karmaiya, Sarlahi
DURATION:
3 Months
WORK ACCOMPLISHED:
Bagmati Irrigation Project, Karmaiya, Sarlahi
DURATION:
3 Months
WORK ACCOMPLISHED:
- Topographical survey of the 1050 ha of at higher areas in head reach of western canal of Bagmati Irrigation Project
- Design of solar/electrical lift irrigation system with open well pumping as well as tubewell pumping
- Cost estimates of solar/electrical lift irrigation systems
CLIENT:
RAAS Engineering Consultancy (P) Ltd and GO Information Consult (P) Ltd. J/V
DURATION:
May 2021 – July 2021
WORK ACCOMPLISHED:
RAAS Engineering Consultancy (P) Ltd and GO Information Consult (P) Ltd. J/V
DURATION:
May 2021 – July 2021
WORK ACCOMPLISHED:
- Preparation of risk maps of three districts including Dolakha District, Sindhuli District and Solukhumbu district.
- Preparation of GIS based risk analysis of flood risk map, landslide risk map, fire susceptibility map, earthquake risk, erosion susceptibility map etc.
CLIENT:
Province Government, Ministry of Physical Infrastructure Development, Building Housing and Urban Development Division, Bagmati Province, Hetaulda, Makawanpur
DURATION:
3 Months
WORK ACCOMPLISHED:
Province Government, Ministry of Physical Infrastructure Development, Building Housing and Urban Development Division, Bagmati Province, Hetaulda, Makawanpur
DURATION:
3 Months
WORK ACCOMPLISHED:
- Preparation of inventory and general assessment of conditions of all the significant public facility systems which support the land uses, analyze the future requirements and present the strategy of development/socio-economic infrastructure development for a modern provincial capital.
- Design of solar/electrical lift irrigation system with open well pumping as well as tubewell pumping
- Cost estimates of solar/electrical lift irrigation systems
Toggle ContentCLIENT:
Mega Dang Valley Irrigation project, Tulsipur, Dang
DURATION:
3 Months
WORK ACCOMPLISHED:
Mega Dang Valley Irrigation project, Tulsipur, Dang
DURATION:
3 Months
WORK ACCOMPLISHED:
- Designed storage and irrigation infrastructures to assure reliable availability of irrigation water for agricultural practices for 140 ha command area.
- Topographical survey of dam site and irrigation area.
- Design of 15m high earthen dam for storage to provide lift irrigation, design of water distribution pipe system and other structures.
- Detailed cost estimate of the earthen dam and irrigation system.
2020
CLIENT:
WaterAid Nepal
DURATION:
October 2019 – January 2020
WORK ACCOMPLISHED:
WaterAid Nepal
DURATION:
October 2019 – January 2020
WORK ACCOMPLISHED:
- Toilets rehabilitation and new construction plan for 10 schools and 1 community in Lahan Municipality.
- Water supply rehabilitation and new construction plan for 10 schools in Lahan
- Waste water Management plan including septic tank and soak pit/ soak trenches in 10 schools in Lahan
- Cost estimate of WASH in 10 schools and 1 community in Lahan.
- Preparation of bidding document
CLIENT:
Babai Irrigation Project, Department of Water Resource and Irrigation, Bardia, Nepal
DURATION:
October 2019 – January 2020
WORK ACCOMPLISHED:
Babai Irrigation Project, Department of Water Resource and Irrigation, Bardia, Nepal
DURATION:
October 2019 – January 2020
WORK ACCOMPLISHED:
- Preparation of detailed flood protection/ River Training master plan for Lohandra River including recommendation of flood control measures from base of the mountain to Nepal-India boarder (61.1km long).
- Hydrologic and hydraulic analysis of flood in Lohandra River
- Socio-economic analysis of the study area
- Computation of detailed cost estimate of recommended measures with economic analysis
- Detailed design of gabion retaining walls for flood control (165m), earthen embankment with gabion mattresses (115km including both banks), gabion spurs (25 nos), drainage outlets (84 nos) and access ramps in dikes (44 nos).
CLIENT:
Water Supply and Sanitation Division No.1, Hetauda, Makwanpur, Nepal.
DURATION:
December 2019 – July 2020
WORK ACCOMPLISHED:
Water Supply and Sanitation Division No.1, Hetauda, Makwanpur, Nepal.
DURATION:
December 2019 – July 2020
WORK ACCOMPLISHED:
- Detail design of water supply scheme
- Topographical survey of water supply scheme
- Detail cost estimate
CLIENT:
Purbakhola Rural Municipality, Ringneraha, Palpa, Nepal.
DURATION:
April 2020 – June 2020
WORK ACCOMPLISHED:
Purbakhola Rural Municipality, Ringneraha, Palpa, Nepal.
DURATION:
April 2020 – June 2020
WORK ACCOMPLISHED:
- Detailed design of earthen dam and its appurtenances including spillway and protection works required
- Carried out detail survey work on dam site and prepared detailed drawings of survy and design
- Preparation of detailed cost estimate for proposed dam construction works
CLIENT:
Sunkoshi Marin Multipropose Diversion Project, Department of Water Resource and Irrigation
DURATION:
December 2019 – April 2020
WORK ACCOMPLISHED:
Sunkoshi Marin Multipropose Diversion Project, Department of Water Resource and Irrigation
DURATION:
December 2019 – April 2020
WORK ACCOMPLISHED:
- Survey of Marin River in Sindhuli District for a stretch of 47km with the application of UAV (Drone) and DGPS/RTK GPS with creation of ortho-rectified image and DEM of the river to generate the plan, contouring, cross section and profile of the river and the flood plain.
- Hydrological and Hydraulic study of the Marin River with simulation of high flood of the river to determine the extent and severity of flood with the application of hydraulic model and GIS.
- Design of flood protection works required for Mrin River in the stretch including design of flood protection embankment and spurs along the banks of the river
- Identify existing irrigation systems and drain outlets along the banks of Marin River, carry out detail design if irrigation intakes and drain outlets.
- Detailed cost estimates of recommended flood protection works, irrigation intakes and drain outlets.
2019
CLIENT:
Babai Irrigation Project, Baidi, Bardia
DURATION:
March 2019 – June 2019
WORK ACCOMPLISHED:
Babai Irrigation Project, Baidi, Bardia
DURATION:
March 2019 – June 2019
WORK ACCOMPLISHED:
- Detailed design of command area development works of Uttarkulo Irrigation System, 790 ha, in Western Canal System of Babai Irrigation Project
- Design of canal system, canal structures and tertiary blocks for command area development works
- Use of Unmanned Aerial Vehicle (drone) and DGPS/RTK GPS for detail survey of the command area development of Uttarkulo Irrigation System.
CLIENT:
Department of Water Resources and Irrigation, Jawalakhel, Lalitpur (Nepal)
DURATION:
April 2019 – July 2019
WORK ACCOMPLISHED:
Department of Water Resources and Irrigation, Jawalakhel, Lalitpur (Nepal)
DURATION:
April 2019 – July 2019
WORK ACCOMPLISHED:
- Inventory survey of watershed management measure works in the East Rapti Watershed in Lohar, Manahari, Handikhola and Bhimphedi Areaincluding locating and collecting the data of all the existing water induced disaster risk reduction structures with their GPS coordinates.
- Assessment of existing watershed management measure works and evaluates the impact including technical and socio-economic status of the existing protection measures
- Recommendation and design of additional water induced disaster risk reduction measures including the cost estimating and drawings of the proposed works.